City of San Mateo Home

Welcome to the City of San Mateo's Legislative Meeting Portal

This page is where you can find information about decisions being made by your elected and appointed officials. The City Council is the first legislative body to migrate to this page. Eventually all agendas, minutes and media for each City Council, Board, Commission, and Standing Committee meeting will be posted on this page. Please continue to visit the individual Board/Commission until the full migration is complete, which is anticipated by December 2015. We will advise through the City’s subscription ‘Notify Me’ service when a migration has occurred. To sign up to receive notifications about any board or commission please visit this link: http://www.cityofsanmateo.org/list.aspx

Instructions for use: Archived meetings are arranged by date, with the most recent at the top of the list. Click on the Media link to watch the meeting with documents, or the Agenda / Minutes links to see the back-up material only. You can also search using keywords in the Search box to find a specific information.

Questions? Issues? Please contact the City Clerk’s office at (650) 522-7042 or email us at polds@cityofsanmateo.org

Share to Facebook Share to Twitter Bookmark and Share
File #: 2018-899   
Title: Wastewater Treatment Plant Immediate Action Projects - Package II - Agreement
Attachments: 1. Att 1 - Agreement, 2. Att 2 - Bid Summary
TO: City Council

FROM: Drew Corbett, City Manager

PREPARED BY: Public Works Department

MEETING DATE: Monday, January 07, 2019

SUBJECT:
title
Wastewater Treatment Plant Immediate Action Projects - Package II - Agreement

label
RECOMMENDATION
recommendation
Approve an agreement with Myers & Sons Construction, LLC for construction of the Wastewater Treatment Plant Immediate Action Project - Package II in an amount not to exceed $6,340,000; establish a contingency fund of $634,000; and authorize the Public Works Director to execute the agreement in substantially the form presented and issue change orders within the contingency.

body
BACKGROUND
The Clean Water Program includes improvements to the wastewater treatment plant (WWTP) to eliminate sanitary sewer overflows and unauthorized discharges. Immediate Action Projects provide rehabilitation to an aging WWTP facility with components dating back to the 1930's and 1950's. To maintain continuous WWTP operations in the event of single points of failure, additional solids processing equipment, piping, and controls are required. This construction package will install large diameter buried concrete pipe, a centrifuge, multiple pumping systems, and a sludge hopper, and includes sludge tank cleaning and other piping improvements.

In accordance with Municipal Code section 3.60.030, a competitive public process was used to obtain bids for this service. A Notice Inviting Sealed Proposals and Bidding Documents was issued to advertise the project on September 16, 2018. Bids were received and opened on October 19, 2018, with the following results:

Contractor
Bid Amount
Myers & Sons Construction, LLC
$6,340,000
Anderson Pacific Engineering Construction, Inc.
$6,990,000
Disney Construction, Inc.
$7,095,000

The low bid of $6,340,000 is 9.4 percent below the engineer's estimate of $7,000,000. Staff recommends awarding the agreement to Myers & Sons Construction, LLC based on staff's determination that Myers & Sons Co...