City of San Mateo Home

Welcome to the City of San Mateo's Legislative Meeting Portal

This page is where you can find information about decisions being made by your elected and appointed officials. The City Council is the first legislative body to migrate to this page. Eventually all agendas, minutes and media for each City Council, Board, Commission, and Standing Committee meeting will be posted on this page. Please continue to visit the individual Board/Commission until the full migration is complete, which is anticipated by December 2015. We will advise through the City’s subscription ‘Notify Me’ service when a migration has occurred. To sign up to receive notifications about any board or commission please visit this link: http://www.cityofsanmateo.org/list.aspx

Instructions for use: Archived meetings are arranged by date, with the most recent at the top of the list. Click on the Media link to watch the meeting with documents, or the Agenda / Minutes links to see the back-up material only. You can also search using keywords in the Search box to find a specific information.

Questions? Issues? Please contact the City Clerk’s office at (650) 522-7042 or email us at polds@cityofsanmateo.org

Share to Facebook Share to Twitter Bookmark and Share
File #: 2018-903   
Title: Contracts with Contingency Component - Update
Attachments: 1. Att 1 - Contingency Status for Active Projects, 2. Att 2 - Completed Projects with Contingencies
TO: City Council

FROM: Drew Corbett, City Manager

PREPARED BY: Public Works Department

MEETING DATE: Monday, January 07, 2019

SUBJECT:
TITLE
Contracts with Contingency Component - Update

LABEL
RECOMMENDATION
RECOMMENDATION
Receive the report on contingency fund expenditures for the period from July 1, 2015 through October 31, 2018, and approve an additional $3,000 contingency for the 39th Avenue Reconstruction Project.
BODY
BACKGROUND
The City Council has awarded contracts and authorized contingency funds to allow flexibility by the Department Director to authorize additional work or change orders up to the approved contingency amount. The contingency amount is typically 10% of the total contract. This approach allows projects to continue without having to return to the City Council for approval of change orders.

The current report shows all active contracts citywide with contingencies greater than $25,000 awarded from July 1, 2015 through October 31, 2018. This report also includes an attachment that shows completed projects with contingencies from this same period. These updates are provided three times annually at a City Council meeting in January, May, and September.

During the preparation of this report, it was discovered that change orders for the 39th Avenue Reconstruction Project exceeded the $70,000 contingency by $2,702. The project is complete, and there will be no additional expenditures. Staff requests approval for an additional $3,000 contingency to conclude this project.

BUDGET IMPACT
Sufficient funds are available in the 39th Avenue Reconstruction Project (467774) for the additional $3,000 contingency.

The remainder of this item is an informational update with no budget impact. Sufficient funds have been allocated to each of the contracts including the contingency amounts.

ENVIRONMENTAL DETERMINATION
This item is being presented for informational purposes only and is therefore not a project subject to CEQA review.